Daokhanong Station Construction Update (November 2027) - MRT Purple Line South
Project: MRT Purple Line, Tao Poon - Rat Burana Section (Kanchanaphisek Ring Road)
Current Status: Construction of bored piles for the elevated Daokhanong Station is underway.
Traffic Impact:
Road Closure: One lane is closed in each direction on Somdet Phrachao Taksin Road, near Ploi Kasem Building to Soi Somdet Phrachao Taksin 41 (approximately 300 meters). This closure facilitates the construction of the main track and Daokhanong Station.
Duration: The closure is in effect 24 hours a day from March 7, 2023, to October 20, 2027.
Remaining Lanes: Three lanes remain open in each direction.
Contractor: Italian-Thai Development Public Company Limited (Contract 5: Daokhanong - Khru Nai section)
Progress (as of September 2027): Civil works are 20.84% complete.
Daokhanong Station Details:
Location: Near Daokhanong Market.
Access Points: Two entry/exit points:
Near a 4-story commercial building close to Khlong Bang Sakae, on the outbound side of Somdet Phrachao Taksin Road.
Near a 2-story commercial building close to Khlong Bang Sakae, on the inbound side of Somdet Phrachao Taksin Road.
MRT Purple Line Project Overview:
Total Length: 23.63 kilometers
Underground Section: 14.29 kilometers with 10 stations.
Elevated Section: 9.34 kilometers with 7 stations.
Park and Ride: Available at Bang Pakok and Rat Burana stations (both inbound and outbound) on Suksawat Road.
Purple Line MRT Construction Update (September 2024)
Take a look at the innovative "pipe roof" construction technique being used at Democracy Monument Station, right in front of the Queen Sirikit Gallery!
📢Purple Line MRT from Tao Poon to Krunai on 31 October 2024 as reported on 10 November 2024 :⚙🚝🥳
0. Overall Civil Works is 44.21% done to be finished in December 2028 and opened in December 2029
1. Contract 1: Tunnels and subway stations Tao Poon - National Library by CKST Joint Venture + PL : 58.84 % done
2. Contract 2: Tunnels and subway stations National Library - Phan Fah by CKST Joint Venture + PL : 50.11% done
3. Contract 3: Tunnels and subway stations Phan Fah - Memorial Bridge near Ban Khaek intersection by Italian Thai Development PCL - NWUR MRT : 40.27 % done
4. Contract 4: Tunnels and subway stations Memorial Bridge near Ban Khaek intersection - Dao Khanong by Unique Engineering and Construction PCL : 43.04 % done
5. Contract 5: Elevated tracks and 7 Elevated stations Dao Khanong - Krunai along with Maintenance Center along with Park and Ride by Italian Thai Development PCL : 22.14 % done
6. Contract 6: Platelaying by Italian Thai Development PCL : 35.20% done
🟣 Heavy Rail Transit total distance of 23.63 km with 17 stations including 14.29 km subways with 10 subway stations 🚇 and 9.34 km elevated track with 7 stations 🚆
🟣 4 Park&Ride buildings on both sides of Bang Pakok and Rat Boorana
🌳 Cement Hydrolic used in this project on 30 September is 207,745.403 metric tons 37.10% of about 560,000 metric tons.
🌳 This has effectively cut down the carbon dioxide equivalence by 10,802.761 metric tons
🌳 This is equal to growing trees of 1,137,132 trees
https://www.facebook.com/MRTPurplelinesouth/posts/535200049296510
Here's a translation of your Thai text, along with some helpful formatting:
Sharing some progress photos!
🚧 Construction progress of Contract 5: Dao Khanong - Khru Nai section, as of the end of October 2024, is at 22.14% overall. This includes the installation of crossbeams at the ticket concourse and platform levels at Yaek Pracha Uthit Station, Phra Pradaeng Station, and Khru Nai Station.
📌 All operations strictly comply with safety, environmental, and traffic measures.
📍 Italian-Thai Development Public Company Limited is the contractor for the construction of the elevated track and stations, train depot, and park-and-ride buildings for the Purple Line Project, Tao Poon - Rat Burana (Kanchanaphisek Ring Road) section, Contract 5: Dao Khanong - Khru Nai section.
Purple Line Progress: Tunneling Under the Chao Phraya River
Ambitious Underground Project Takes Shape
Bangkok's ambitious Purple Line extension continues to advance, with tunneling operations underway on four key contracts. The 23.63 km southern section, stretching from Tao Poon to Rat Burana, involves a complex underground network spanning 14.29 km.
This massive undertaking requires the excavation of twin tunnels, reaching depths of 30-40 meters, and the construction of several underground stations. Seven tunnel boring machines (TBMs) are currently deployed across the project, with Contracts 1 and 2 utilizing three TBMs each, and Contracts 3 and 4 employing two each.
Progress Update:
* Contracts 1 & 2 (Tao Poon - National Library - Phan Fa): Joint venture CKST-PL, comprising Ch. Karnchang Public Company Limited (CK) and Sino-Thai Engineering and Construction Company (STEC), has already bored nearly 3 km of tunnels.
* Contract 4 (Saphan Phut - Dao Khanong): Unique Engineering and Construction Public Company Limited is preparing to launch its TBMs in December 2024, with tunneling commencing in January 2025 and expected to be completed by January 2026.
* Contract 3 (Phan Fa - Saphan Phut): A joint venture between Italian-Thai Development Public Company Limited and Nawarat Patanakarn Public Company Limited (ITD-NWR MRT) is tackling this challenging section, which includes a crucial river crossing. Tunneling under the Chao Phraya River is scheduled to begin in September 2025, with completion anticipated in September 2026.
Engineering Feat:
Contract 3 presents a unique engineering challenge: boring a 200-meter tunnel beneath the Chao Phraya River. This echoes the groundbreaking achievement of the Blue Line extension, which successfully navigated a similar subterranean passage between Sanam Chai and Itsaraphap stations. The Purple Line tunnel, however, will plunge even deeper, reaching a depth of approximately 20 meters below the riverbed.
This depth is necessary to accommodate the existing urban landscape and avoid disrupting older buildings and communities above. Despite the challenges, engineers expect the river crossing to take approximately 15 days, similar to the time required for tunneling through regular terrain.
Looking Ahead:
As of October 2024, the Purple Line Southern Project is 44.21% complete. With all six contracts progressing steadily, the line is on track to open for service by the end of 2071, providing a much-needed boost to Bangkok's public transportation network and easing congestion in the rapidly growing metropolis.
Phra Pradaeng Station Accelerates Crossbeam Installation for the MRT Purple Line South (Nov 2024)
Purple Line Project, Tao Poon - Rat Burana Section, Kanchanaphisek Ring Road
Italian-Thai Development Public Company Limited, the contractor for the construction of elevated tracks and stations, Park & Ride buildings, in Contract 5 (Dao Khanong - Khru Nai section), has recently made significant progress in installing crossbeams on the ticketing level of Phra Pradaeng Station.
Construction machinery has been brought in for the station's entrances and exits.
Progress as of October 2024 for Contract 5 (Dao Khanong - Khru Nai):
* Civil works are 22.14% complete.
Phra Pradaeng Station:
* Located at the intersection of Nakhon Khuean Khan Road, about 1.6 km from Rat Burana Station.
* Elevated station with 4 entrances and exits.
You cannot post new topics in this forum You cannot reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum