October 29, 2024 - Dr. Permsak Pia-yura, a member of the Senate, raised concerns about the progress of the "Ban Phai - Mahasarakham - Roi Et - Mukdahan - Nakhon Phanom" double-track railway construction. He highlighted delays in construction and expressed public anxiety over whether the project will be completed on schedule, as the contract is set to end in 2027.
Ban Phai - Nakhon Phanom Railway Construction Project, Contract 1: Ban Phai - Nong Phok Section
5 November 2024
🚃 Progress Report for October 2024
As of 25 October 2024
Isan Double-Track Railway Construction Project: Ban Phai - Mahasarakham - Roi Et - Mukdahan - Nakhon Phanom
Contract 1: Ban Phai - Nong Phok
Cumulative planned progress: 33.766%
Cumulative actual progress: 14.354%
Behind schedule by: -19.412%
Chiang Khwan Station, Roi Et Province, is a small-sized railway station. It is part of Contract 1, Ban Phai - Nong Phok section, of the Ban Phai - Mukdahan - Nakhon Phanom double-track railway project. This 180-kilometer section has a budget of 27,095 million baht and is being constructed by the AS-Cho Thavee & Associates joint venture.
This video is about the construction progress of the railway tunnel in the "บ้านไผ่-นครพนม" railway project. The tunnel is located at kilometer 115, in the area of Chiang Khwan District, Roi Et Province.
The tunnel is a small, rectangular-shaped structure designed for pedestrians, small vehicles, and animals to pass under the railway. The video shows that the construction of the tunnel has progressed significantly.
This project is part of the new double-track railway line in the Northeast of Thailand, connecting "บ้านไผ่ - มหาสารคาม - ร้อยเอ็ด - ยโสธร - มุกดาหาร - นครพนม". The total distance of this railway line is 180 kilometers.
The construction includes:
* Railway tracks (both elevated and ground level)
* Railway station buildings (ground level)
* 9 stations
* 6 railway stops
* 1 railway junction
* 3 container yards
* 1 large container depot
* 43 railway crossing bridges
* 126 rectangular tunnels
* Other civil works such as drainage systems, pedestrian bridges, and fences
The total budget for this construction is 27,195 million baht. As of November 2024, the project has progressed by approximately 14.35%, which is behind schedule by about 19.02%.