The new Nakhon Pathom train station building is now open for service. You can buy tickets at the new location. The new station building is about 50 meters past the old station. It is big and spacious, especially the long platform. However, some parts are not yet finished. The passenger lifts that cross the platform are now available. https://www.facebook.com/teerapol.fongkaimuk/posts/9121898794553316
Double-Track Railway Construction Project, Lopburi-Pak Nam Pho Section
Department of Rail Transport Monitors Construction and Inspects Readiness for Double-Track Railway Opening, Lopburi - Pak Nam Pho Section
February 10, 2025: Officers from the Department of Rail Transport visited the Nakhon Sawan railway station, the Centralized Traffic Control (CTC) building, and the Pak Nam Pho railway station to monitor the construction and inspect the readiness for the opening of the double-track railway, Lopburi - Pak Nam Pho section. The construction of station buildings, platforms, and railway tracks has been completed. Currently, the installation of signaling and telecommunication systems is underway.
Double-track railway "Lopburi - Pak Nam Pho" to open in mid-2025
The Department of Rail Transport has been inspecting the readiness of the double-track railway project between Lopburi and Pak Nam Pho. The project is scheduled to begin testing in May 2025 before opening for service in the middle of the year.
The project includes the construction of a new Lopburi 2 station, which will be used for long-distance trains. The original Lopburi station will continue to be used for local trains. The Lopburi Transport Department will also organize two bus routes to connect the two stations.
The double-track railway project between Lopburi and Pak Nam Pho is divided into three contracts:
* Contract 1: Ban Kab - Khok Krathiam section (32 kilometers). This contract includes the construction of the new Lopburi 2 station, which is the longest elevated railway structure in Thailand.
* Contract 2: Tha Khae - Pak Nam Pho section (116 kilometers). This contract includes the construction of six new stations and the replacement of 11 existing stations.
* Contract 3: Signal and telecommunications systems. This contract is currently under construction and is 54.88% complete.
The Department of Rail Transport will continue to monitor the project to ensure that it can be opened for service in mid-2025 as planned. The double-track railway will help to reduce travel time, improve safety, and connect the transportation system to tourist routes in the North.
Here are some additional details about the project:
* The new Lopburi 2 station is an elevated station with three floors: a ground floor, a ticket sales floor, and a platform floor.
* The original Lopburi station will continue to be used for ordinary trains, suburban trains, and local trains.
* The Chan Sen station is a new station with a cargo container transfer area.
* The Nakhon Sawan station is a new large station with a train control building (CTC).
* The Pak Nam Pho station is a new station that replaces the old station. It is a renovated station that retains the original station's design.
The double-track railway project between Lopburi and Pak Nam Pho is an important infrastructure project that will benefit the people of Thailand. It will help to improve transportation, reduce travel time, and boost the economy.
This is a news article about the progress of the double-track railway project in Thailand. Here's a summary of the key points:
Double-track railway project: The State Railway of Thailand (SRT) is working on a double-track railway project in the northern region of the country. This project will allow trains to run in both directions simultaneously, which will increase the number of trains that can run and reduce travel times.
New Lopburi 2 station: As part of the project, a new elevated station called Lopburi 2 is being built. This station will be used for long-distance trains, while the existing Lopburi station will be used for local trains.
E-Token system: The SRT will be using an electronic token (E-Token) system to manage train traffic on the new double-track line. This system will help to improve safety and efficiency.
Bus connections: The Lopburi Provincial Transport Office is planning to provide public bus services to connect passengers to the new Lopburi 2 station.
Overall, the double-track railway project is expected to improve transportation in the northern region of Thailand. It will make it easier and faster for people to travel by train, and it will also help to reduce traffic congestion.
Here are some additional details about the project:
Location: The double-track railway line is being built between Lopburi and Pak Nam Pho, which are both located in the northern region of Thailand.
Distance: The total distance of the line is 148 kilometers.
Completion date: The project is expected to be completed in the middle of 2025.
Benefits: The project is expected to bring a number of benefits to the region, including reduced travel times, increased safety, and improved connectivity.