Update HSR Construction from Saraburi to Donklang Railway halt in May 2025.
Iron Wheels Roaming
May 5, 2025 #hsr #hsrthailand #train
*Pls touch CC for your language.
In this clip, we will look at Khlong Phreaw, which is preparing to cast a balanced cantilever beam across Khlong Phreaw.
And at Saraburi Station, they are assembling a balanced cantilever beam cast frame from the pier.
Then it will be Contract 4-6 from Saraburi to the contract point.
A little past the Ban Don Klang stop.
The construction is progressing.
There is an entry into the area following the clip we filmed in March.
Which is the first trip.
Update construction HSR Thailand from Ban Pho to Rangsit in April 2025
Iron Wheels Roaming
May 7, 2025 #hsr #hsrthailand #train
*Pls touch CC for your language.
In this clip, it will be a cruise in contracts 4-3, 4-4 and 4-2
From Ban Pho to Rangsit.
There is progress in many points compared to what we saw in mid-March.
Anyway, go and watch the clip..
Contract 4-3, Nuan Nakhon-Ban Pho section
Distance: 23 km.
Contractor: C.A.N. Joint Venture Co., Ltd.
Progress on March 25, 2025: 53.02%
Contract 4-4, Chiang Rak Noi Maintenance Center
Contractor: Italian-Thai Development Public Company Limited
Progress on March 25, 2025: 39.06%
Contract 4-2
Don Mueang-Nuan Nakhon section
Distance: 21.80 km.
Contractor: Unique Engineering and Construction Public Company Limited
Progress on March 25, 2025: 3.10%