**Touch CC for your subtitlies
Continue from the previous clip..
Starting from the 4th-5th contract before crossing Ayutthaya Road..
The latest announcement was last month..
That UNESCO has passed..
Next, the contract will be signed under the new and revised contract..
In June...
As of today.. we still don't know if it has been done yet..
Let's wait and hear more news..
After that.. within 1 month, the first construction start letter was issued: NTP (Notice to Proceed).
If according to the announcement, it will be July..
As for the NTP for the construction of the station building, wait another 6 months.. will follow later..
**We'll wait and hear more news..
But today, this clip...
Let's see the route that the high-speed train will run on first..
Take a photo first..before entering the construction area along the entire 13.3 km. route
of contract 4-5...
After that, if we enter the area..we won't see the same images..
And we will take the train to Phra Kaew station in this clip..
Look at contract 4-6 at the end of this month.
You will see that construction is continuing..
I'll go and look at the clip..😊😊
And we will take the return trip to see the beginning of contract 4-5 in another round..😊😊😊
Starting at the beginning of contract 3-1 at the container loading point
At Kaeng Khoi Junction..
1 month has passed, the first pier has been casted..
And it should follow closely because they are drilling and casting piles
And making foundations at the same time..
Long until crossing the road to the end of the line
Entering the Chinee Ville Village
And driving piles across the track that we are riding to the Thap Kwang School side
Contract 3-1 is fast..
But in this clip, we only watch up to Muak Lek first..
The clip will be too long...
The construction continues until Muak Lek Station..
There is a tunnel and a running track between the tunnels.
It is contract 3-2, and it continues..
Let's go watch the clip..This clip is not long..😊😊
Construction of the high-speed railway from Muak Lek to Pak Chong in early July 2025
Continuing from the previous clip
Let's continue from Muak Lek to Klang Dong Pang Asok, the horse stairs to Pak Chong first.
There is continuous construction.
The day we went to film was July 4, 2025.
Starting from the staff housing area at Muak Lek Station.
They have started to demolish it to make way for pile driving..
Clearing the area continuously..
Then they will open the hole to cast the foundation before reaching the bridge over the Muak Lek Canal.
They have a lot of it..
After crossing the Muak Lek Canal and going until before reaching Nam Phu Temple, they are also preparing to cast the foundation..
You can see that at Nam Phu Temple.. a new crematorium has been built..
This means that the original crematorium must be demolished.. to make way for construction..
Crossing the track around the Muak Lek basin to the middle of the forest.
At the bridge neck before going down to the balm factory..
The piers are being casted to support the runway all the way to the balm factory..
Then it will be a long ground level route cutting straight into the railway area.
After passing the Central Dong station, it will continue with Contract 1-1.
The area is being cleared to continue with the ground level runway.
Last month, it was still covered with forest.
Straight from Pang Asok station.
It is continuing..
Preparing to be an elevated runway to divert to the other side.
And at the beginning of Contract 3-1, after removing the old track,
they have entered the area to dig and cast piles..
You will soon see the piers being raised.. after waiting for a long time..
This clip will only go to Pak Chong.. The next clip will continue..
Continuing from the previous clip..
It is still the 3-3 contract..
We took the train to see from Pak Chong
Passing the new station
Passing the Lam Takhong Dam
Passing the Lam Takhong Tunnel
Until the exit of the tunnel on the Khlong Pai side..
The progress.. is still not much compared to last month..
It will be a detailed work.. in some places..
Anyway, go watch the clip..
Continuing from the previous clip..the last clip at the beginning of July..
Starting from the railway tunnel on the Khlong Pai side..
You will see the progress without interruption.
Let's keep watching..until Korat station..😊😊