Construction progress update for the Orange Line electric train project, Bang Khun Non - Thailand Cultural Centre section, as of the end of November 2025. Reported on 11 December 2025.
Overall progress: 18.85%
Civil works progress: 20.39 %
Electric train system progress: 7.05%
*Note: Electric train system progress for the Orange Line electric train project, Thailand Cultural Centre - Min Buri (Suwinthawong) section, is 31.74%.
As of the end of November 2025, over 112,083.56 tons of hydraulic cement, or 28.02%, have been used in the construction of the Orange Line electric train project.
This is equivalent to a greenhouse gas reduction of 5,828.345 tons of carbon dioxide equivalent.
This is equivalent to planting 613,510 trees.
Follow project details on:
Facebook: Orange Line Electric Train Project, Bang Khun Non - Thailand Cultural Centre section
https://www.facebook.com/permalink.php?story_fbid=122153261480701333&id=61571039999518
You cannot post new topics in this forum You cannot reply to topics in this forum You cannot edit your posts in this forum You cannot delete your posts in this forum You cannot vote in polls in this forum