📢Purple Line MRT from Tao Poon to Krunai on 30 November 2025 as reported on 11 December 2025 :⚙🚝🥳
0. Overall Civil Works is 66.14% done to be finished in December 2028 and opened in December 2029
1. Contract 1: Tunnels and subway stations Tao Poon - National Library by CKST Joint Venture + PL : 79.65% done
2. Contract 2: Tunnels and subway stations National Library - Phan Fah by CKST Joint Venture + PL : 73.73% done
3. Contract 3: Tunnels and subway stations Phan Fah - Memorial Bridge near Ban Khaek intersection by Italian Thai Development PCL - NWUR MRT : 60.33% done
4. Contract 4: Tunnels and subway stations Memorial Bridge near Ban Khaek intersection - Dao Khanong by Unique Engineering and Construction PCL : 64.84% done
5. Contract 5: Elevated tracks and 7 Elevated stations Dao Khanong - Krunai along with Maintenance Center along with Park and Ride by Italian Thai Development PCL : 47.19% done
6. Contract 6: Platelaying by Italian Thai Development PCL : 53.24% done
🟣 Heavy Rail Transit total distance of 23.63 km with 17 stations including 14.29 km subways with 10 subway stations 🚇 and 9.34 km elevated track with 7 stations 🚆
🟣 4 Park&Ride buildings on both sides of Bang Pakok and Rat Boorana
🌳 Cement Hydrolic used in this project on 30 November is 334,864.80 metric tons or 59.80% of about 560,000 metric tons.
🌳 This has effectively cut down the carbon dioxide equivalence by 17,412.970 metric tons
🌳 This is equal to growing trees of 1,832,944 trees