🚇Construction Progress of Denchai - Chiang Rai - Chiang Khong Double-Track Railway as of 30 November 2025 reported on 11 December 2025 🚇
😊👉 Overall: Accumulated Work Progress Goal: 47.871 %
Accumulated Actual Work Progress: 48.620 %
Progress: 0.749%
😊👉 Contract 1: Denchai - Ngao including Ngao station along with the First Tunnel (1.175 km) and the Second tunnel (6.240 km) in Song district of Phrae - 104 km at 26,560 million Baht
Construction period 15 February 2022 - 14 January 2028 (2160 days)
Contractor: ITD (Italian Thai Development PCL) - NW (Naowarat Phatthanakarn PCL)
Accumulated Work Progress Goal: 51.324 %
Accumulated Actual Work Progress: 46.382 %
Progress: -4.942%
Platelaying has been started from Denchai by ITD
😊👉 Contract 2: Ngao - Chiang Rai station (including the third tunnel (2.700 km) at Mae Ka township, Mueang district of Phayao but excluding bot Ngao station and Chiang Rai station) - 135 km at 26,890 million Baht
Contractor: CK (Ch. Karn Chang PCL) -STECON [Sino Thai Engineering Construction PCL] - DC2 (Buriram Phanasit Co. Ltd. - Domestic Contractor 2)
Construction period: 15 February 2022 - 14 January 2028 (2160 days)
Accumulated Work Progress Goal : 50.275%
Accumulated Actual Work Progress : 54.589%
Progress: 4.314%
😊👉 Contract 3: Chiang Rai - Chiang Khong including Chiang Rai station and the Fourth tunnel in Doi Luang district of Chiang rai - 87 km at 19,385 million Baht
Contractor: CK (Ch. Karn Chang PCL) -STECON [Sino Thai Engineering Construction PCL] - DC3 (Chiang Mai Construction Co. Ltd. - Domestic Contractor 3)
Construction period: 15 February 2022 - 14 January 2028 (2160 days)
Accumulated Work Progress Goal: 39.805 %
Accumulated Actual Work Progress: 43.405 %
Progress: 3.600%
#### Major Tunnels (4 tunnels)
🚇😊👉 the First Tunnel (1.175 km) => * **Song Tunnel (Phrae)**
Accumulated Work Progress Goal: 100.00%
Accumulated Actual Work Progress: 95.70%
Progress: -4.30 % (Delayed 4.30%)
This tunnel is almost done - hope to get done by the end of 2025
Length without both gate facades: 1,059 m
North: Up Track - 967.90 m / Down Track- 0 m)
South: Up Track - 0 m / Down Track 0 m)
🚇😊👉 the Second tunnel (6.240 km) => * **Ngao Tunnel (Lampang)**
Accumulated Work Progress Goal: 63.81%
Accumulated Actual Work Progress: 65.15%
Progress: 2.34%
Length without both gate facades: 6,211 m
North: Up Track - 1,556.50 m / Down Track - 1,581.20 m)
South: Up Track - 2,537.10 m / Down Track - 2,545.60 m)
🚇😊👉 the third tunnel (2.700 km) => * **Mae Ka Tunnel (Phayao)**
Accumulated Work Progress Goal: 59.47 %
Accumulated Actual Work Progress: 68.37 %
Progress: 8.90 %
Length without both gate facades: 2,700 m
North: Up Track - 0 m / Down Track 0 m)
South: Up Track - 0 m / Down Track - 0 m)
🚇😊👉 the Fourth tunnel (3.400 km) => * **Doi Luang Tunnel (Chiang Rai)** - the first breakthrough
Accumulated Work Progress Goal: 54.68 %
Accumulated Actual Work Progress: 63.77 %
Progress: 9.09 %
Length without both gate facades: 3,400 m
North: Up Track - 0 m / Down Track 0 m)
South: Up Track - 0 m / Down Track - 0 m)