Double track railway, Den Chai, Chiang Rai, Chiang Khong
20 April 2024 3:54 p.m.
📢Announcement📢
CKST-DC 2 and DC 3 joint venture, contractor for contract 2, Ngao-Chiang Rai section, and contract 3, Chiang Rai-Chiang Khong section. Notification of the installation plan and transportation route for precast concrete I beam parts (I GIRDER) for construction of railway bridges (RAILWAY BRIDGE) and railroad bridges (OVERPASS BRIDGE), starting with installation at Railway Bridge No. 152 (RB 152 ) Mae Ka Subdistrict area Mueang Phayao District, Phayao Province
The concrete beams used in both contracts, approximately 14,800 pieces, were transported from 3 factories, distributed in each area, namely the factory in Don Sila Subdistrict, Wiang Chai District, Chiang Rai Province, the Huai Sak Subdistrict Factory, Mueang Chiang Rai District, Chiang Rai Province, and the Subdistrict Factory. Don Sichum, Dok Khamtai District, Phayao Province, with the transportation route covering the area of Ngao District, Lampang Province, Mueang Phayao District, Dok Khamtai District, Phu Kam Yao District, Phayao Province and Pa Daed District, Wiang Chai District, Wiang Chiang Rung District, .Doi Luang, Chiang Khong District, Chiang Rai Province
📍Installation plan Starting from 20 May 2024 to 30 December 2025
🚛🚛Transportation time from the factory to the work site is between 9:00 p.m. - 4:00 a.m.
📞Emergency contact channel: Mr. Bunsaeng Klaichanphong Safety Manager 08 8989 9435
This may cause users of the route to have inconvenience in traveling. and there may be loud noises disturbing nearby areas We apologize for the inconvenience on this occasion 🙏🙏