📢Purple Line MRT from Tao Poon to Krunai on 31 January 2024 as reported on 8 February 2024 :⚙🚝🥳
0. Overall Civil Works is 26.26% done to be finished in December 2028 and opened in December 2029
1. Contract 1: Tunnels and subway stations Tao Poon - National Library by CKST Joint Venture + PL : 34.08 % done
2. Contract 2: Tunnels and subway stations National Library - Phan Fah by CKST Joint Venture + PL : 32.28 % done
3. Contract 3: Tunnels and subway stations Phan Fah - Memorial Bridge near Ban Khaek intersection by Italian Thai Development PCL - NWUR MRT : 24.13 % done
4. Contract 4: Tunnels and subway stations Memorial Bridge near Ban Khaek intersection - Dao Khanong by Unique Engineering and Construction PCL : 26.46 % done
5. Contract 5: Elevated tracks and 7 Elevated stations Dao Khanong - Krunai along with Maintenance Center along with Park and Ride by Italian Thai Development PCL : 12.49 % done
6. Contract 6: Platelaying by Italian Thai Development PCL : 12.57 % done
🟣 Heavy Rail Transit total distance of 23.63 km with 17 stations including 14.29 km subways with 10 subway stations 🚇 and 9.34 km elevated track with 7 stations 🚆